How long does electric screwdriver mass production take?
Electric screwdriver mass production usually takes about 10–20 days after the final sample, specifications, battery, packaging, and order details are approved.
A practical guide is:
Standard model with no customization: about 7–10 days
Logo or simple packaging customization: about 10–15 days
Custom color, bit combination, or accessories: about 15–20 days
Custom torque, speed, battery, PCB, or structural changes: longer because additional sampling and engineering validation are required
New mold or full ODM project: usually requires separate tooling and development time before mass production can start
The production lead time mainly depends on:
Motor, gearbox, PCB, and battery availability
Bit quantity and material
Product color and surface treatment
Logo process
Packaging
Assembly capacity
Aging and reliability testing
Torque and functional inspection
Order quantity
Compliance requirements
For ToolQeen standard precision electric screwdriver orders, around 10–15 days is typical for 1,000 pcs once all specifications are frozen and materials are ready.
To avoid delays, buyers should confirm the golden sample, BOM, torque settings, battery model, bit configuration, logo, packaging artwork, QC standard, and shipping method before mass production starts.